The Abiola-Onijemo Bridge, Lagos

The Abiola-Onijemo Bridge, Lagos

The Abiola-Onijemo Bridge construction in Lagos, Nigeria is about to enter its final stage of construction. This 9-span, 135m reinforced concrete bridge, will connect the Abiola and Onijemo streets.

To expedite the site works, the Contractor elected to prefabricate the main longitudinal girders and the transverse planks, for which they created an on-site fabrication yard.

Kedmor would like to thank the Contractor for their professional work and excellent collaboration.

Contractor – Geld Construction Ltd

Client – Lagos State Ministry of Transport

 

Kedmor Team: Micha Petri, Tom Bauer, Itamar Netzer, Olga Tarasova, Eilon Glazer, Nitay Barak.

Photo Credit: Geld Construction Ltd

New Partners at Kedmor!

New Partners at Kedmor!

We are delighted to announce that Mor Machlev and Gal Edri have joined Amir Kedar, Raz Mor & Micha Petri as Partners, significantly strengthening our leadership team.

Both Mor and Gal joined the practice as young engineers, during their final years of university, and have continuously developed their technical and managerial skills.

Gal began his career at Kedmor, working with Micha Petri in the Yavne branch for two years, until moving to the main office in Givatayim. Since 2018, Gal has led a team, specializing in the design of bridges, railroad electrification projects, and complex prestressed concrete elements.

Mor Joined Kedmor in 2015, became a Team Leader in 2019 and moved to Myanmar in 2020, to establish our practice there. Mor specializes in the design of segmental bridges and complex interchanges, and has also been deeply involved in the implementation of BIM within the practice.

We are confident that Gal and Mor will play integral roles in shaping the future success of Kedmor Engineers.

Operation Iron Swords

Operation Iron Swords

On 7th October 2023, Israel was attacked by Hamas, committing the worst atrocity against the Jewish people since the Holocaust.

As our country goes to war, a significant part of the Kedmor team have been called up to the army reserves. Needless to say, we are incredibly worried, but so proud of them, and are doing our best to support their families during this time.

We are also supporting the wider community, delivering food and supplies to those evacuated from around Gaza, and to the army.

In the meantime, our Israel office continues to function.

We pray for the success of the IDF, and for peace in Israel.

ה׳ עוז לעמו יתן. השם יברך את עמו בשלום

Construction begins on Havatzelet Bridge, Netanya

Construction begins on Havatzelet Bridge, Netanya

Construction is about to commence on the Havatzelet bridge in Netanya.

This 5-span vehicular bridge, crosses Israel’s Avichail National Park, and is designed to connect a new neighborhood in the north of Netanya to Route 2. The bridge is 150m long and is composed of two separate cast-in-place concrete decks with shared abutments.

Kedmor have acted as the Structural Engineer of Record and the Architects on this project. The entire project was modelled in Revit, and analyzed using Sofistik advanced finite element software. Complex Dynamo scripts were created to link between the Revit and Sofistik models, to aid the detailing and coordination of the prestressing tendons.

We wish the site team success during construction!

 

Client – ח.ל.ת החברה לפיתוח ולתיירות נתניה

Project Manager – Eyal Nitsan

Road Designer – P.G.L

Contractor - Ramet

Shana Tova

Shana Tova

Wishing all our clients, colleagues, friends & family a happy, healthy and sweet New Year.

Shana Tova!

Parking Lot 4/9 on Ramot Interchange

Parking Lot 4/9 on Ramot Interchange

The construction of the Public Transportation Parking Lot 4/9 on Ramot Interchange in Jerusalem was recently completed.

We provided value engineering services for the Contractor, optimizing the design of around 250 precast, pre-stressed concrete girders.

The design incorporated the full BIM process, and we provided 3D digital deliverables.

A huge thanks to our colleagues at Yaron-Shimoni-Shacham, the Designer of Record, for their cooperation.

 Contractor: Danya Cebus Ltd.

 Client: Moriah Jerusalem Development Corporation

 Photo Credit: Chezki Mozes - Ein Hanetz

Student Intake 2023-2024

Student Intake 2023-2024

Kedmor welcomes this year’s placement students: Yoav Milgrom, Talia Dychtwald, Einav Dori, and Chen Somech, from the Ben-Gurion University of the Negev.

Each will be involved with our projects, gaining valuable practical design office experience.

They will also receive guidance for their final university projects, from our Team Leaders.

Please get in touch if you’d like to be part of next year’s student intake.

The opening of Arlosoroff Light-Rail Station

The opening of Arlosoroff Light-Rail Station

Thrilled about the opening of The Tel-Aviv Light-Rail Red-Line, which includes Arlosoroff Underground Station, designed by Kedmor!

This underground station structure comprises of water-tight ‘outer-box’ diaphragm walls, which helped facilitate the temporary works requirements, during ground excavation and the construction of the main station inner-box.

The XL Canopy, one of the key pieces of the Red-Line stations, located above the Arlosoroff station had been meticulously detailed as well. The connection nodes weigh up to ca. 950 kg each and are 200 mm of solid steel, welded to the profiles. Their design included volumetric finite-element analysis, with the help of Lusas FE software.

Kedmor are the structural Engineer of Record for this complex underground structure, provided engineering support throughout construction.

With thanks to our colleagues at RHDHV, IBI Architects, Joseph Klein Soil Consultant and NTA for their collaboration throughout the project.

Photo Credits: Arcadis - IBI Group

The Great Ruaha Bridge

The Great Ruaha Bridge

Introducing the Great Ruaha Bridge in Tanzania, currently under construction!

This 133m long symmetrical steel girder structure gracefully spans the river with its 41-51-41m spans, supported by two mid-piers and two abutments, all founded on shallow footings, which sit on the bedrock.

The construction of this impressive bridge utilizes the incremental launching method, allowing for seamless construction without obstructing the river’s flow.

Credits:

Client: Tanzania National Roads Agency

Contractor: SBI International Holdings AG - RCC Tanzania

Tom Bauer, Itamar Netzer, Meital Toledano, Yelena Shtofblat ,Rachel Ovadia, Raz Mor.

Bezalel Pavilion

Bezalel Pavilion

‘The Pavilion’ is a voluntary project, in conjunction with the Bezalel Academy of Art & Design in Jerusalem, that Kedmor has been involved with since 2018.

The objective is to design and build a pavilion, to be temporarily located at the entrance to the Architecture department of the university.

This year, the project focused on the use of Ytong blocks, kindly donated by Ytong Factory.

The students used AI to generate a series of different schemes and the alternative with the highest probability of success was chosen for construction.

The structural geometry was optimized using Rhino software, to achieve the largest possible shadow, within the given constraints of the challenge.

Kedmor Engineers provided structural input for the project, utilizing SOFiSTiK advanced finite analysis software, to analyze the stability of the structure.

We had a lot of fun supporting the project, and relish the opportunity to collaborate with the future Architects of the world.

Purim celebration

Purim celebration

Last week kedmor family celebrated Purim Holiday.

Our workers came with their children and we had lots of fun.

Kedmor Engineers in the annual CivilEng Race

Kedmor Engineers in the annual CivilEng Race

Kedmor Engineers runners participated in the annual CivilEng Race.

It was a well-organized sport event and a great opportunity to meet our colleague.

Well done everyone.

welcome our interns

Kedmor welcomes, Eden Lorman , Nitay Barak, Inbar Talker, Oz Hoyda from Ben-Gurion University of the Negev, for their internship.

Each will be involved with our projects, gaining valuable practical experience in the design office.

They will also receive guidance for their final university projects from our Team Leaders.

Please get in touch if you’d like to be part of next year’s student intake.

HAPPY JEWISH NEW YEAR


Happy Hebrew New Year and Happy holidays.

Wishing everyone all the best.

Kedmor Engineers.

BIA Bridge, Ghana

BIA Bridge, Ghana

The construction of the bridge is finished.
The work on the road is in progress and the bridge will remain closed to traffic until the completion of the road along its entire length.

Photos by: Amandi Invensments LImited LTD

2411 Road Ofakim

2411 Road Ofakim

Bridge #4 is a cast in-situ post tensioned bridge 25 meter long.
The bridge carries road 2411 over a desert trail.
The bridge’s superstructure was cast in one pour.

Photos by: Etgar- Engineering & Consultancy LTD

HETZEL BRIDGE

HETZEL BRIDGE

Ducts arrangement – main casting of the bridge (casting stage 1)


Pictures by : Shachar Perez